Construction work on Angra 3 Nuclear Power Plant 1405 MW located in Angra dos Reis, Rio de Janeiro, Brazil commenced in Q3 2024, after the project was announced in Q1 1974. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2031. To learn more about the Angra 3 Nuclear Power Plant 1405 MW project, buy the profile here.
The project involves the construction of a nuclear power plant with a generation capacity of 1,405MW on an 82,000m2 area in Central Nuclear Almirante Álvaro Alberto Complex (CNAA), Angra dos Reis, Rio de Janeiro, Brazil.
The project includes the following:
1. Construction of a nuclear power plant
2. Construction of power stations
3. Construction of pressure vessels
4. Construction of warehouses
5. Construction of substations
6. Laying of transmission lines
7. Installation of switchyards
8. Installation of water treatment systems
9. Installation of steam generators
10. Installation of moisture separator reheaters
11. Installation of safety equipment
Construction on the project, spread across 8.2 hectares, is expected to be completed by Q4 2031.
For more details on the Angra 3 Nuclear Power Plant 1405 MW project, buy the profile here.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalData