Construction work on Mountain Home Air Force Base Water Treatment Plant and Pump Station located in Idaho, the US commenced in Q3 2024, after the project was announced in Q1 2023. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q3 2026. To learn more about the Mountain Home Air Force Base Water Treatment Plant and Pump Station project, buy the profile here.

The project involves the construction of a water treatment plant and pump station with a capacity to process 3.5 million (3,500,000) gallons per day at Mountain Home Air Force Base in Idaho, the US.

Smarter leaders trust GlobalData

The project includes the following:

1. Construction of a pump station
2. Construction of storage tanks
3. Construction of an administration building
4. Construction of an outdoor control system
5. Installation of water distribution pipelines

Construction on the project is expected to be completed by Q3 2026.

For more details on the Mountain Home Air Force Base Water Treatment Plant and Pump Station project, buy the profile here.

This content was updated on 31 January 2025