Construction work on LOGI’Q Hasuda Logistic Facility located in Hasuda, Saitama, Japan commenced in Q3 2024, after the project was announced in Q2 2022. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q1 2026. To learn more about the LOGI’Q Hasuda Logistic Facility project, buy the profile here.

The project involves the construction of a 98,370.24m2, four-story logistics facility on 4.68ha of land in Hasuda City, Saitama Prefecture, Japan.

Smarter leaders trust GlobalData

The project includes the following:

1. Construction of storage units
2. Construction of an office space
3. Construction of loading and unloading facilities
4. Construction of 174 car parking spaces
5. Installation of safety and security systems

Construction on the project, spread across 4.68 hectares, is expected to be completed by Q1 2026.

For more details on the LOGI’Q Hasuda Logistic Facility project, buy the profile here.

This content was updated on 20 December 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.