Construction work on Fundici Solar Park 55 MW located in Sevilla, Andalusia, Spain commenced in Q2 2023, after the project was announced in Q1 2018. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2024. To learn more about the Fundici Solar Park 55 MW project, buy the profile here.
The project involves the construction of the Fundici solar plant in Guillena, Seville, Andalusia, Spain.
The project includes the following:
1. Construction of a 55MW solar plant
2. Construction of substations
3. Construction of access and internal roads
4. Installation of solar panels
5. Installation of solar trackers
6. Installation of 19, 2,250kVA, GAMESA E-SE-I inverters
7. Installation of 50, 132/20kV, MVA transformers, with load regulation and a grounding reactance
8. Installation of electrical and mechanical equipment
9. Laying of a 7.95km, 132kV overhead and 500m underground transmission lines
Construction on the project is expected to be completed by Q4 2024.
Spain-based Ingenieria Y Suministros Asturias is the architect and engineering design consultant for the Fundici Solar Park 55 MW, while Ayuntamiento de Sevilla is the planning authority.
For more details on the Fundici Solar Park 55 MW project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.