Construction work on Frankeneng 150 kV Substation located in Ede, Gelderland, Netherlands commenced in Q3 2024, after the project was announced in Q1 2023. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2028. To learn more about the Frankeneng 150 kV Substation project, buy the profile here.
The project involves the construction of a 150/50 kV substation in Gelderland, Netherlands.
The project includes the following:
1. Construction of a substation
2. Construction of a control station
3. Construction of parking spaces
4. Installation of a 100MVA transformer
5. Installation of safety and security systems
Construction on the project is expected to be completed by Q4 2028.
For more details on the Frankeneng 150 kV Substation project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.