Construction work on Vulcanesti to Chisinau 400KV Transmission Line and Substation located in Moldova commenced in Q4 2023, after the project was announced in Q1 2014. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2025. To learn more about the Vulcanesti to Chisinau 400KV Transmission Line and Substation project, buy the profile here.
The project involves the construction of a 158km, 400kV single circuit overhead transmission line from Vulcanesti to Chisinau in Moldova.
The project includes the following:
1. Construction of a 600MW back-to-back converter substation
2. Construction of a new Central Dispatch Center
3. Installation of an Energy Management System
4. Installation of a supervisory control and data acquisition system
5. Installation of three single-phase 400/330kV auto-transformers
6. Installation of a power dispatch and metering system
7. Installation of a Meter Management System
8. Upgrades to two existing substations
Construction on the project is expected to be completed by Q4 2025.
For more details on the Vulcanesti to Chisinau 400KV Transmission Line and Substation project, buy the profile here.