Construction work on Larivot Biomass Power Plant 120 MW located in Cayenne, Guyane, French Guiana commenced in Q4 2023, after the project was announced in Q1 2017. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2026. To learn more about the Larivot Biomass Power Plant 120 MW project, buy the profile here.

The project involves the construction of a biomass power plant in Larivot, French Guiana.

Smarter leaders trust GlobalData

The project includes the following:

1. Construction of a 120MW liquid biomass power plant on a 10ha area
2. Construction of access roads
3. Installation of chimneys
4. Installation of boilers
5. Installation of transformers
6. Laying of a 14km pipeline to transport liquid oil from the plant

Construction on the project, spread across 10 hectares, is expected to be completed by Q4 2026.

For more details on the Larivot Biomass Power Plant 120 MW project, buy the profile here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

GlobalData’s Construction Projects database tracks over 220,000 new construction projects valued at >$25m from announcement to completion across all countries and sectors.