Construction work on Herrera Solar Power Plant 93.62 MW located in Palencia, Castille and Leon, Spain commenced in Q4 2024, after the project was announced in Q2 2019. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2025. To learn more about the Herrera Solar Power Plant 93.62 MW project, buy the profile here.
The project involves the construction of the Herrera solar power plant in Herrera de Pisuerga in the province of Palencia, Castile and Leon, Spain.
The project includes the following:
1. Construction of a 93.62MW solar plant with 30/132kV substations on a 228.51ha area
2. Construction of a control building with the installation of auxiliary equipment
3. Installation of 174,990 monocrystalline silicon photovoltaic modules
4. Installation of 2,658 photovoltaic trackers
5. Installation of 333 sectioning and protection boxes
6. Installation of inverter and transformer
7. Installation of transformers with a capacity of 400kV
8. Installation of electrical and mechanical equipment
9. Laying of a 400kV and 30/132kV overhead transmission line with a length of 2.59km
10. Laying of a fence of 17.44km
Construction on the project, spread across 228.51 hectares, is expected to be completed by Q4 2025.
For more details on the Herrera Solar Power Plant 93.62 MW project, buy the profile here.