Construction work on Cidade de San Caetano Administrative Complex Redevelopment located in Galicia, Spain commenced in Q4 2023, after the project was announced in Q1 2017. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2026. To learn more about the Cidade de San Caetano Administrative Complex Redevelopment project, buy the profile here.
The project involves the construction of the Cidade de San Caetano Administrative Complex in San Caetano, Galicia, Spain.
The project includes the following:
1. Construction of two four-story (two underground and two aboveground) green rooftops integrated administrative buildings with a total gross floor area of 12,000m2 with a seating capacity of 650 employees, a nursery facility with 270 seats, offices and meeting rooms and parking facilities with 255 spaces, as well as the installation of solar panels, elevators, security and ventilation systems
2. Construction of two three-story administrative green rooftop buildings on a 0.58-ha area with a total gross floor area of 23,228m2 and underground parking facilities in phase II
Construction on the project is expected to be completed by Q4 2026.
Spain-based IDOM Consulting, Engineering, Architecture SAU is the architect and engineering design consultant for the Cidade de San Caetano Administrative Complex Redevelopment, while Government of Galicia is the planning authority.
For more details on the Cidade de San Caetano Administrative Complex Redevelopment project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.