According to GlobalData, the value of the UK construction market is forecast to decline by 1.9% in real terms in 2024, having grown by 4.1% in 2023. A key growth market will be the infrastructure market, with output rising by 3.1% in real terms. GlobalData tracks and profiles all major construction projects from announcement to completion. For further insight on this market, buy the latest profiles here.

Here are the top five solar energy construction projects that commenced in the UK in Q1 2024, according to GlobalData’s construction projects database.

Smarter leaders trust GlobalData

Report-cover

Data Insights Construction Project Profiles

Buy the Profiles

Data Insights

The gold standard of business intelligence.

Find out more

1. Cotmoor Lane Solar Farm 50 MW

The project involves the construction of the 50MW Cotmoor Lane Solar Farm on 107.81ha of land at Cotmoor Lane in Southwell, Nottinghamshire, East Midlands.

Construction work started in Q1 2024 and is expected to be completed in Q4 2024.

2. Ashorne Solar Farm 49.9 MW

The project involves the construction of the 49.9MW Ashorne Solar Farm on 100ha of land at Chesterton Fields Farm, Fosse Way, Ashorne Hill, in Royal Leamington Spa, Warwickshire.

Construction work commenced in Q1 2024 and is expected to finish in Q4 2024.

3. Doverdale Solar Farm 50 MW

The project involves the construction of the 50MW Doverdale Solar Farm on 63.41ha of land at Southall Lane in Doverdale, Worcester.

Construction work started in Q1 2024 and is forecast to complete in Q4 2024.

4. Dunfermline Solar Farm 30 MW and Battery Storage

The project involves the construction of a 30MW solar farm and 49.9MW/60MWh battery storage on 45ha of land in Dunfermline, Fife.

Construction work commenced in Q1 2024 and is expected to be completed in Q1 2026.

Pennon Group Plc acquired the project from Ampyr Developments Pte Ltd (AMPYR).

5. Claydon Solar Farm 45 MW and Battery Energy Storage System

The project involves the construction of the 45MW Claydon Solar Farm and 10MW Battery Energy Storage System (BESS) on 106.74ha of land at Claydon Farm in Claydon, Tewkesbury, Gloucestershire.

Construction work started in Q1 2024 and is expected to be completed in Q4 2024.

For more details on the latest construction projects, buy the profiles here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

GlobalData’s Construction Projects database tracks over 220,000 new construction projects valued at >$25m from announcement to completion across all countries and sectors.