Construction work on Bakeoven Solar Project 303 MW located in Oregon, the US commenced in Q1 2023, after the project was announced in Q1 2020. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q2 2026. To learn more about the Bakeoven Solar Project 303 MW project, buy the profile here.

The project involves the construction of a 303MW solar power plant on 1,100ha of land in Wasco County, Oregon, the US.

Smarter leaders trust GlobalData

The project includes the following:

1. Construction of a substation
2. Construction of solar platforms
3. Installation of generators
4. Installation of transformers
5. Installation of solar panels
6. Laying of 18Km transmission lines with 230 kV capacity

Construction on the project, spread across 1100 hectares, is expected to be completed by Q2 2026.

For more details on the Bakeoven Solar Project 303 MW project, buy the profile here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.