Construction work on Huizhou Dongjiang Gas Turbine Thermal Power Project located in Huizhou, Guangdong, China commenced in Q1 2023, after the project was announced in Q2 2020. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q1 2026. To learn more about the Huizhou Dongjiang Gas Turbine Thermal Power Project project, buy the profile here.
The project involves the construction of a Huizhou Dongjiang Gas Turbine Thermal Power Plant 1070MW in Guangdong.
The project includes the following:
1. Construction of a powerhouse
2. Construction of fuel storage tanks
3. Construction of a substation
4. Construction of combustion chambers
5. Construction of other related infrastructure
6. Installation of two 9F natural gas turbines
7. Installation of generators
8. Installation of transformers
9. Laying of transmission lines
10. Installation of related equipment
Construction on the project is expected to be completed by Q1 2026.
For more details on the Huizhou Dongjiang Gas Turbine Thermal Power Project project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.