Construction work on the $25m Ramme solar park 48 MW located in Central Jutland, Denmark commenced in Q2 2022. It was announced in Q1 2021.
The project involves the construction of a 48MW solar park in Ramme, Jutland, Denmark.
The project includes the following:
1. Construction of substations
2. Installation of horizontal tracking systems
3. Installation of solar panels and transformers
4. Laying of transmission lines
5. Installation of safety and security systems.
Construction on the project is expected to be completed by Q4 2022.
Owners of the project include Denmark-based GreenGo Energy Group A/S, Skovgaard Invest.